An Industrial visit to PSGiTech Campus Water Treatment Plant on 27th October 2021
A total of 50 students of III year Civil Engineering visited the water treatment plant functioning at PSGiTech Campus as part of the water supply Engineering course. Dr. M. Devasena accompanied the students
The current drinking water supply line is starting from River Bhavani via an intermediate pumping station @ Kumaran Kundram to Neelambur Campus and then it moves to PSGCAS, PSGIMSR, PSG Tech Hostels, PSG School and finally to the PSG Tech Campus.
Source: River Bhavani
Conveyance: Ductile Iron Pipes
Pressure: 50-60 Kg/cm2 (No entry of contaminated water)
Design Capacity: 45 lakh litre
Students were able to understand the treatment units such as cascade aeration, Plain sedimentation and slow sand filtration.